The Energiz.AR Plan, is an ongoing public infrastructure project devised by the Ministry of Public Works, with three main objectives regarding the development of the national energy network in the near future.

- To increase the share of nuclear and renewable sources in energy generation.

- To gradually phase out fossil fuel and other non-renewable means as primary sources of energy generation, leaving only strategic reserves to be used in case of contingencies.

- To have a nationwide total installed generating capacity of 50,000 MW.

Ongoing works

TBD

.....

Planned works

TBD

.....

Completed works

- TdF-1, TdF-2 wind farms
Locations: 44 km NW of Río Grande and 2 km S of Puerto Soledad, Tierra del Fuego Province
Constructed by: YTL Corp., Yau Lee Corp., and Waskita Industries (Indonesia)
Operated by: Agua y Energía S.E. - 100%

Specifications:
1x 50 MW
1x 12 MW

Total cost: USD $143,000,000

*

- Mar Chiquita Nuclear Power Plant
Location: Mar Chiquita, Buenos Aires Province
Constructed by: Rosatom (Russia)
To be operated by: Nucleoeléctrica Argentina S.E. - 100%

Specifications:
4x VVER-TOI (5,200 MW)

Total cost: USD $18,270,400,000

*

- Acantilado del Cóndor hydroelectric dam
Location: 180 km W of Puerto Santa Cruz, Santa Cruz Province
Constructed by: SOMISA, SACDE (Argentina)
To be operated by: Agua y Energía S.E. - 100%

Specifications:
1,140 MW nameplate capacity

Total cost: USD $15,861,000,000

*

- La Barrancosa hydroelectric dam
Location: 115 km W of Puerto Santa Cruz, Santa Cruz Province
Constructed by: SOMISA, SACDE (Argentina)
To be operated by: Agua y Energía S.E. - 100%

Specifications:
600 MW nameplate capacity

Total cost: USD $8,652,000,000

*

- El Tambolar hydroelectric dam
Location: 26 km E of Calingasta, San Juan Province
Constructed by: SOMISA, SACDE (Argentina)
To be operated by: Agua y Energía S.E. - 100%

Specifications:
75 MW nameplate capacity

Total cost: USD $1,082,000,000

*

- Güer Aike wind farm
Location: 4 km S of La Esperanza, Santa Cruz Province
Constructed by: CIAEE, SACDE (Argentina)
To be operated by: Agua y Energía S.E. - 100%

Specifications:
1 x 1000 MW

Total cost: USD $2,310,000,000

*

- José A. Balseiro Nuclear Power Plant
Location: 6 km SW of Villa Dique Florentino Ameghino, Chubut Province
Constructed by: Rosatom (Russia)
To be operated by: Nucleoeléctrica Argentina S.E. - 100%

Required specifications:
2x VVER-TOI (2,600 MW)

Total cost: USD $7,285,200,000

*

- Río Gallegos Nuclear Power Plant
Location: 40 km N of Río Gallegos, Santa Cruz Province
Constructed by: Rosatom (Russia)
To be operated by: Nucleoeléctrica Argentina S.E. - 100%

Required specifications:
2x VVER-TOI (2,600 MW)

Total cost: USD $7,285,200,000

*

- Santa Catalina solar farm
Location: Santa Catalina, Jujuy Province
Constructed by: SACDE, INDARCCO, SOMISA, Tensolite S.A. (Argentina)
To be operated by: Genneia S.A. - 25%, 360 Energy Solar S.A. - 25%, Agua y Energía S.E. - 25%, National Institute of Indigenous Affairs - 5%, Provincial Government - 20%

Required specifications:
600 MW nameplate capacity

Total cost: USD $780,000,000

-----

Current total generating capacity: 61,664 MW

Natural Gas/Coal: 28,875 MW (47.4%)

Solar: 900 MW (1%)

Wind: 5,249 MW (8.5%)

Hydroelectric: 14,588 MW (23.6%)

Nuclear: 12,052 MW (19.5%)